Custom Glove Production Timeline

Your custom glove is made specifically for you and typically takes approximately 7–8 weeks to complete. All timelines are estimates and may vary based on manufacturing schedules and the complexity of your design.

  1. 1

    Days 1–2

    Order Received

    Your order is reviewed and confirmed.

  2. 2

    Days 2–4

    Sent to Manufacturing

    Your specifications are submitted to the factory.

  3. 3

    Weeks 1–2

    Production Queue

    Your glove waits for its production slot.

  4. 4

    Weeks 1–2

    Cutting & Assembly

    Leather is selected, cut and prepared.

  5. 5

    Weeks 3–4

    Sewing

    Components are sewn together.

  6. 6

    Weeks 5–6

    Lacing & Finishing

    The glove is laced, finished and inspected.

  7. 7

    Weeks 6–7

    Factory Shipping

    The finished glove ships to our facility (transit is typically 5–7 days).

  8. 8

    Weeks 7–8

    Final Inspection & Shipping

    We inspect your glove and ship it to you with tracking.

Factory shipment is not customer shipment. Gloves first come to our facility for a final quality check.